October 27, 2026 · Archipartners Design

Paradise Valley Hillside Building Committee Review for Custom Homes

Lots with a 10% slope or greater need HBC approval before you can submit a building permit application

Paradise Valley requires Hillside Building Committee review before accepting a building permit application for any lot with a building-site slope of 10 percent or more, according to the Town of Paradise Valley's Building Permit Application Information. This adds a separate approval stage before plan review begins and applies to new custom homes, major additions, and guest houses on sloped terrain.

The Hillside Committee review adds approximately 6 to 12 weeks to the permitting timeline before building-department plan review begins, according to Fenn Rogers's "Building in Paradise Valley: What Makes It Different." You'll need to complete and clear this stage before the Town will accept your building permit application.

Timeline After Hillside Committee Approval

Once the Hillside Building Committee approves your project and the Town accepts your building permit application, plan review takes up to 15 business days per review round, according to the Town of Paradise Valley's Building Permit Application Information. After the plans are approved, the Town takes an additional 3 to 5 business days to issue the permit.

Full building permit review through Paradise Valley's Building Safety Department takes 6 to 14 weeks, according to Fenn Rogers. That timeline begins only after you've cleared the Hillside Building Committee stage on a sloped lot.

Permit path for a sloped Paradise Valley lot

  1. Check the building-site slope

    10 percent or more means Hillside Building Committee review

  2. Hillside Building Committee review

    About 6 to 12 weeks (Fenn Rogers)

  3. Town accepts the building permit application

  4. Plan review

    Up to 15 business days per review round

  5. Permit issued

    3 to 5 business days after the plans are approved

Source: Town of Paradise Valley; Fenn Rogers

Additional Requirements for New Homes and Major Remodels

Additional requirements apply to every new house, regardless of value, or to remodel projects with a value of $500,000 or greater, according to the Town of Paradise Valley's Building Permit Application Information. Most Paradise Valley custom home and major addition projects will trigger these heightened review standards.

Prior to the first footing inspection, all property pins and property lines must be identified, according to the Town's Building Permit Application Information.

What to Do Before You Start Design

Check your lot's slope before you hire anyone to draw plans. If your building site has a 10 percent slope or greater, factor in 6 to 12 weeks for Hillside Building Committee review before the Town will accept your building permit application, then up to 15 business days per plan-review round after that.

We handle custom home drafting and permit plans in Arizona, and every set opens with a code-analysis sheet. If you're ready to get a quote for your Paradise Valley project, reach out here.

FAQ

Frequently asked questions

  • When does Paradise Valley require Hillside Building Committee review?

    When the building site has a slope of 10 percent or more, according to the Town of Paradise Valley’s Building Permit Application Information. The review comes before the Town will accept a building permit application, and applies to new custom homes, major additions and guest houses on sloped terrain.

  • How much time does Hillside Building Committee review add?

    About 6 to 12 weeks before building-department plan review begins, according to Fenn Rogers’s “Building in Paradise Valley: What Makes It Different.”

  • How long is plan review after the hillside approval?

    Up to 15 business days per review round, and the Town takes another 3 to 5 business days to issue the permit once the plans are approved, according to the Town’s Building Permit Application Information.

  • Which Paradise Valley projects face the additional requirements?

    Every new house, regardless of value, and remodels valued at $500,000 or more, according to the Town’s Building Permit Application Information. Before the first footing inspection, all property pins and property lines must be identified.

Have a project that fits this conversation? Send a sketch and a sentence.

Begin a project →

We reply within one business day.

Paradise Valley Hillside Building Committee Review for Custom Homes · Archipartners Design