FIELD GUIDE
Office and Shop Build-Out Field Guide: checks to run before you sign the lease
Ten checks, the stop signs, and what seven Phoenix-area cities say about change of use, certificate of occupancy, accessibility, fire and signs, before you sign a lease.
A lease is easy to sign and hard to undo. Most of the surprises in a tenant improvement come from the space, not from the drawings: the zoning may not allow your use, the new use may count as a different occupancy, or the restroom may not be accessible. This guide lists the checks to run first. It is for offices and shops. We draw tenant improvements for offices and shops up to 3,000 sf with no structural change. Larger spaces, structural work, and restaurants, gyms, churches or event spaces go to a registered architect, and we will refer you. Food uses have their own guide.
Updated November 23, 2026 · Free · one email with the link
Built from the city pages of Phoenix, Mesa, Scottsdale, Chandler, Gilbert, Tempe, Glendale. Anywhere else, check your own city’s page.
One email with the link. We don’t sell your address; you can unsubscribe with one click.
5-MINUTE GO / NO-GO
Answer these before you spend money.
Each check is a yes or no. A “no” or a “don’t know” is something to settle first.
Does the zoning at this address allow your kind of business?
Zoning is checked before anything else. Mesa and Glendale tell you to confirm the use is allowed first, and Chandler says a Certificate of Occupancy needs the zoning to match the business. Some uses need a Use Permit from the city, which is a separate approval.10,17,13
Is your use the same as the last tenant's, or does it change the occupancy class?
Mesa says a tenant who changes use or occupancy class needs a tenant improvement permit even when no walls move. Phoenix needs a certificate for a remodel that changes the occupancy type. A change can bring fire and exit requirements the old tenant never met.9,5
If the use changes to a higher hazard class, does the building need fire sprinklers?
Phoenix Fire has a policy that a building under 2,500 sf needs sprinklers when its occupancy changes to a higher hazard level. Ask the fire department which level your old and new uses fall in before you sign.6
Is there an accessible route from the parking to your door, and an accessible restroom?
Phoenix asks the plans to show accessible parking, accessible routes, and the location and size of the accessible restrooms. Federal rules put the accessible entrance, route and restroom first when a tenant alters space. If the restroom is not accessible, add that cost to your budget.4,1,3
Have you set aside money for the accessible path of travel, up to 20 percent of the work?
The federal rule treats path-of-travel work as too much when it costs more than 20 percent of the cost of altering the main work area. Under that limit, you must do it. Over it, you still do as much as the limit allows, in a set order. Work split into small jobs within three years is added together.1,2
Does the layout have enough exits for the number of people it will hold?
Phoenix wants an exit plan showing the longest path to an exit, the number of exits, each room's occupant load and the exit width. Scottsdale asks for the occupancy group and load. Glendale's inspection looks for lit exit signs, working emergency lighting and unblocked exits.4,12,18
Will the landlord let you change the electrical, plumbing and air conditioning you need?
The city asks for mechanical, plumbing and electrical sheets with the permit, and Glendale needs the landlord's signed approval for signs. Your lease decides who may change what and who pays. This guide is not legal advice; read the lease with your own lawyer.4,12,19
Is the space 3,000 sf or less, and will you keep the structure as it is?
That is the limit of what we draw. Glendale also says a space over 3,000 sf needs plans sealed by an Arizona-registered design professional. Over that size, or with structural work, we refer you to a registered architect.17
Do you need a sign, and have you planned its separate permit?
Phoenix takes sign applications at its own counter, apart from the building permit. Glendale needs the landlord's signed approval and an approved tenant improvement permit or certificate first. Your lease may also limit sign size and place.7,19
STOP SIGNALS
If you see any of these, pause.
The zoning does not allow your use
If the city's zoning does not list your use, a Use Permit or a zoning change may be needed. Chandler says a Use Permit goes to City Council. Do not sign until the city tells you in writing what is possible.13,10,17
The new use needs a change of occupancy that triggers sprinklers
Phoenix Fire requires sprinklers in a small building when occupancy moves to a higher hazard level, and a fire alarm can follow a change of use. Sprinklers can cost far more than the build-out. Get the fire department's answer first.6
There is no accessible restroom and no room to add one
Phoenix plans must show the accessible restrooms. A restroom that cannot be made accessible can change the whole plan. Measure before you sign.4,1
The landlord will not allow electrical, plumbing or air conditioning changes
Without those changes the permit set cannot match what you plan to build. Get the permission in the lease or in a signed letter before you pay for drawings.4,12
The space has no certificate of occupancy on file
Mesa says a tenant improvement permit is for a building that already has a certificate. Phoenix handles a missing record through its ombudsman. Ask for the record first.10,5
More than 3,000 sf, structural work, or a restaurant, gym, church or event space
We do not draw these. We refer them to a registered architect. For food uses, use our restaurant guide to check the space before you sign.17
WHAT THE CITY WILL ASK FOR
Expect to be asked for these.
A plan set that shows the use, exits and code data
Phoenix and Scottsdale ask for the occupancy, construction type, square footage, sprinkler and alarm information, exits and each room's use. Phoenix also asks for the occupancy of the neighboring suites and a description of the business.4,12
Accessibility information
Phoenix asks for accessible parking, accessible routes and the location and size of the accessible restrooms, and for cost documentation when the accessible route is not made fully accessible.4
A plumbing fixture analysis and mechanical, electrical sheets
Phoenix lists a minimum plumbing fixture analysis, mechanical layouts with ventilation, and electrical plans with panel schedules and load calculations. Some sheets are sealed by a registered engineer. Scottsdale adds COMcheck or an equivalent energy report. We do not state fixture counts here; the plumbing code table for your use decides.4,12
Zoning confirmation for the use
Scottsdale's site plan shows the current zoning. Mesa, Chandler and Glendale tell you to confirm the use with Planning first. Ask Planning in writing.12,10,13,17
Certificate of occupancy for the new tenant
Phoenix, Mesa, Chandler and Glendale all tie the certificate to passing inspections. Glendale asks even a business with no construction to get a No Work certificate in its own name. Ask how your city handles a new tenant in the same use.5,9,13,18
A separate sign permit
Phoenix: sign counter, drawing with sizes, and a licensed electrical contractor for lit signs. Glendale: color plans, the landlord's letter on company letterhead, and an approved tenant improvement permit or certificate first.7,19
YOUR CITY’S RULES
Your city’s rules.
Short notes from each city’s own pages. Rules change, so open the linked page for the current text.
Phoenix4,5,6,7,8
- A certificate of occupancy is needed for a tenant improvement of a newly occupied space and for work that changes the occupancy type. Other projects may get a "green tag".
- The Fire Department policy says a building under 2,500 sf needs sprinklers when its occupancy changes to a higher hazard level, and a change of use can bring a fire alarm.
- Signs go through the signs counter, apart from the building permit. Uses by zoning district are in the online Zoning Ordinance; ask Planning if your use is not clear.
Mesa9,10,11
- A tenant who changes the use or occupancy class needs a tenant improvement permit even with no physical change. The certificate follows the final inspection.
- Confirm the use is allowed in the zoning district first. Permits and plans go through the DIMES portal. Mesa's Permit by Inspection option leaves out work that needs zoning approval.
- Mesa applies the 2024 I-Codes to applications on or after January 8, 2026.
Scottsdale12
- The tenant improvement checklist asks for a registered design professional's seal on every sheet. We draw and do not seal, so name the city when you ask us for a quote.
- The site plan shows the current zoning and a parking analysis. The plans show the existing and the new use and occupancy, and the sprinkler and alarm data.
- Incomplete plans are not accepted for review. Ask about the building code edition; we did not confirm it.
Chandler13,14
- Chandler gives the certificate when inspections show the building meets code and the zoning matches the business. Every business must pass inspection and get one before opening.
- If zoning could fit only with a Use Permit, talk to Economic Development staff. A Use Permit goes to City Council. The city's free Business Location Team helps with the tenant improvement process.
- Chandler adopted the 2024 International Codes with its own amendments (Ordinance 5108).
Gilbert15
- The permits page lists a Tenant Improvement Checklist. Start there.
- The page says commercial work needs an Arizona licensed contractor, and plans may need an Arizona registrant for anything other than a single-family home.
- The free Taking Care of Small Business team helps through to the certificate of occupancy. Ask Gilbert for its building code edition for commercial work.
Tempe16
- Commercial plan review checks tenant improvements for structure, fire safety, accessibility and energy before a permit is issued.
- Plans go in electronically under Tempe's E-Plan guidelines. The page links a Commercial Building Tenant Improvement Project Checklist and handouts.
- Ask Tempe how it handles the certificate of occupancy and use permits for your use; we could not confirm them.
Glendale17,18,19
- Confirm the use with Planning before pursuing a certificate. A space over 3,000 sf needs plans sealed by an Arizona-registered design professional.
- A new business, a change of owner, FEIN or business name needs a certificate in the business name. With no construction, apply for a No Work certificate; a Building Safety inspection follows.
- Signs need the landlord's signed letter on company letterhead, and a new tenant needs an approved tenant improvement permit or a certificate before a sign permit.
COSTS TO EXPECT
Our fee, and building costs where a public source gives one.
Our drawing package for a tenant improvement of an office or shop up to 2,500 sf
Our fee, from the price list
$7,450
Glendale's fee for a No Work certificate of occupancy as printed in its guide (a city fee, not ours)18
Building cost, not our fee
$114.35
FAQ
Frequently asked questions
Do you draw restaurants, gyms or churches?
No. We draw tenant improvements for offices and shops up to 3,000 sf with no structural change. Restaurants, gyms, churches and event spaces, spaces over 3,000 sf, and any structural change are referred to a registered architect. If you are weighing a food space, our restaurant guide at /guides/restaurant-conversion helps you check it before you sign.
What counts as a change of use?
It is a change in how the space is used or in its occupancy class, for example from an office to a shop. Mesa says it needs a tenant improvement permit even with no physical work. Phoenix needs a certificate for a remodel that changes the occupancy type. Ask your city which class your old and new uses are in.
What is the 20 percent rule?
When you alter an area where your business operates, federal rules also ask you to make the path to it accessible: entrance, route, restroom, then phones and drinking fountains. The cost is counted as too much when it passes 20 percent of the cost of altering the main area. You then do as much as that limit allows. Phoenix asks the plans to show the cost documentation when the route is not fully made accessible. Ask your architect or us how it applies to your budget.
How many restrooms do I need?
It depends on your use and how many people the space holds, using the plumbing code table. The cities we read did not print fixture counts on their checklists. Phoenix asks for a minimum plumbing fixture analysis and the accessible restrooms shown on the plans. We work it out for your space once we know the use.
Who does what, the landlord or me?
Your lease decides. In plain words, the landlord's work is usually the building and its shell, and the tenant's work is the inside of your space, but leases differ a lot. The city's certificate belongs to the building in Phoenix, and Glendale needs the landlord's signed letter for signs. We are not lawyers; read the lease with your own lawyer before you sign.
Can I start work before the permit?
Do not start permitted work without the permit. Mesa says its tenant improvement permit covers electrical, plumbing and mechanical alterations, structural changes and safety systems. Light finish work in a move-in-ready space, like painting or flooring, may not need new plans in Mesa. Ask your city before you start.
Is the sign part of the tenant improvement permit?
No. Signs are a separate permit. Phoenix takes sign applications at its own counter. Glendale wants the landlord's signed letter first. Plan the sign early, because your lease may limit it.
What should I send you before I sign the lease?
The address and suite, the square footage, the use you plan, any floor plan or lease sketch, and the last tenant's use if you know it. We reply within one business day. If it is over 3,000 sf, structural, or a restaurant, gym, church or event space, we will refer you to a registered architect.
SOURCES
Where each fact comes from.
Every number in a superscript links to the official page below. Opens in a new tab.
- ADA Title III regulations, 28 CFR Part 36 (incl. 36.403 path of travel)
U.S. Department of Justice (eCFR) · checked November 2026
- ADA Title III primer for businesses
ADA.gov · checked November 2026
- 2010 ADA Standards for Accessible Design
ADA.gov · checked November 2026
- Commercial building permit submittal checklist (PDF)
City of Phoenix · checked November 2026
- Certificate of occupancy
City of Phoenix · checked November 2026
- Fire Prevention explanatory policy manual (PDF)
City of Phoenix Fire Department · checked November 2026
- Signs, frequently asked questions (PDF)
City of Phoenix · checked November 2026
- Zoning Ordinance (online)
City of Phoenix · checked November 2026
- Commercial construction FAQ
City of Mesa · checked November 2026
- Small business assistance
City of Mesa · checked November 2026
- Mesa building code
City of Mesa · checked November 2026
- Administrative review minimum submittal requirements, commercial tenant improvements (PDF)
City of Scottsdale · checked November 2026
- Small business guide 2025 (PDF)
City of Chandler · checked November 2026
- Amendments to the 2024 International Codes (PDF)
City of Chandler · checked November 2026
- Permits, applications and checklists
Town of Gilbert · checked November 2026
- Commercial plan review
City of Tempe · checked November 2026
- Business licenses (tenant improvements and certificate of occupancy)
City of Glendale · checked November 2026
- No work certificate of occupancy guide (PDF)
City of Glendale · checked November 2026
- Sign submittal requirements (PDF)
City of Glendale · checked November 2026
WHEN YOU’RE READY
Want us to draw it?
Send us the address and what you want built. We reply within one business day.