The City Sent Corrections: a Field Guide to answering a plan review letter

Ten checks and the stop signs before you answer a plan review letter, with what seven Phoenix-area cities say about resubmitting, expiring applications and who can submit.

A corrections letter is normal. It is not a "no". It is a list of things the city wants fixed or shown before it can move on. The risk is answering it badly: missing a comment, sending the wrong sheets in the wrong format, or letting the application run out. Sort the comments first. Some you can answer yourself, some need your drafter, and some need an engineer. Every fact below links to an official page. Where a city page does not say, we tell you to ask.

Updated November 23, 2026 · Free · one email with the link

Built from the city pages of Phoenix, Mesa, Scottsdale, Chandler, Gilbert, Tempe, Glendale. Anywhere else, check your own city’s page.

One email with the link. We don’t sell your address; you can unsubscribe with one click.

5-MINUTE GO / NO-GO

Answer these before you spend money.

Each check is a yes or no. A “no” or a “don’t know” is something to settle first.

  1. Do you have the whole letter, every comment, and the marked-up sheets the city sent?

    Glendale says corrections come by email with a marked-up package showing the requested changes. Chandler says you can see the comments in its online portal. Mesa sends a system email when more information is needed. Download everything first. Answering from memory or from a forwarded summary is how comments get missed.21,11,6

  2. Can you tell which comments are a drawing fix, a missing document, a zoning question or an engineering question?

    Mesa keeps separate checklists for building items and for zoning items, so the same letter can mix both. Scottsdale and Mesa checklists list the usual building items: ceiling heights, escape openings, energy, equipment locations. A drawing fix is a drafter’s job. A zoning or engineering comment is not. Label each one before you do anything.7,8,10

  3. Does any comment ask for calculations, a sealed design or a special inspection form?

    Chandler requires sealed truss calculations, or a truss waiver sealed by an Arizona-registered engineer. Mesa asks for engineer-sealed drawings on new homes and pools. Glendale has the engineer of record seal the special inspection form. Tempe lists a "Registered Design Professional Required" handout on its plan review page. If a comment asks for any of this, you cannot answer it with a redrawn sheet.11,6,23,17

  4. Does your site plan match the survey and the real lot, with distances to the property lines?

    Chandler’s manual says the plot plan must show the property lines, every building on the lot, and distances from new structures to the property lines, and that locating the property lines is the owner’s job. A site plan that disagrees with the survey is not a drawing fix. Everything built on it has to be redone.11

  5. Is any comment about setbacks, lot coverage or parking?

    Mesa lists zoning items such as covered parking and garage size in a zoning checklist apart from the building checklist. These are about where and how big the building is, not how it is drawn. If the answer is "it does not fit", the design changes, and that is a redesign, not a correction.8,7

  6. Is your application still active, and do you know the date it runs out?

    Scottsdale treats an application as abandoned 180 days after the last completed correction or approval step, unless you are pursuing it in good faith. Chandler and Scottsdale allow a written extension request before expiration. Phoenix, Gilbert and Tempe pages we read do not state a limit, so ask. Check the date today.9,14,2,16,19

  7. Are you allowed to submit the answer yourself?

    Glendale lets the homeowner or a licensed contractor apply, and a homeowner may prepare drawings for a home improvement if they are accurate, legible and complete. Chandler requires a licensed contractor unless the owner does the work, and always for a home you rent out. State law (A.R.S. 32-1121) covers owners building for their own use, not for sale or rent. Mesa says owner-occupied projects may not need a licensed contractor.22,23,11,1,6

  8. Do you know the format your city wants for the corrected sheets?

    Chandler says keep the original file names and page order, put new sheets at the end, and that reordering causes delays. Phoenix electronic review wants the same file names as the originals so the system can compare versions. Glendale wants a new complete set with every change marked with a delta and a cloud. A good fix in the wrong format can be sent back.12,5,21

  9. Is this a correction before approval, or a change after approval?

    Cities handle the two differently. Phoenix’s standard-plan guideline says changes to approved plans go in as revised sheets only, with a cloud and delta, and a change that adds to the original scope needs a new submittal, application and fee. Chandler takes revisions to approved plans by email with only the affected sheets. Know which one you have before you send anything.4,12

  10. If someone else drew the plans, are they available and did they address every comment?

    Plans you did not draw are plans you cannot easily change. Chandler and Glendale both send a new set back through the same portal, and an incomplete resubmittal can be returned. Ask the drafter to go through the letter line by line and mark each comment answered, in writing. A comment nobody answered is the most common reason a second letter arrives.12,21,5

STOP SIGNALS

If you see any of these, pause.

  • A comment asks for calculations or a sealed design

    A drawing cannot replace an engineer’s calculations or seal. Chandler, Mesa and Glendale each name items that need an engineer to seal. Stop and get the engineer involved before you answer.11,6,23

  • The site plan contradicts the survey

    If the property lines, building position or distances on the plans disagree with the survey, the plans are wrong at the base. Chandler says the owner locates the property lines. Get the survey checked first.11

  • A zoning comment means the design has to move

    Setbacks, lot coverage, parking count and garage size are zoning items. If the building does not meet them, the answer is a redesign, and sometimes a variance request from the city’s planning office. Do not just redraw the sheet.8

  • The application is about to run out

    Scottsdale calls an application abandoned 180 days after the last completed correction or approval step, and Chandler and Scottsdale take extension requests only before the date. Glendale says a permit left too long needs new plans and full fees. Ask for the extension now, in writing.9,14,24

  • The change adds to the original scope

    Phoenix’s standard-plan guideline says a change that adds to the work in the original submittal needs a new submittal, a new application and a new fee. A correction answer is not the place to add a room.4

  • Comments the drafter never addressed

    If the person who drew the plans is gone, or sent a resubmittal that skipped comments, a second letter is likely. Chandler notes that incomplete packages add review cycles and, on a fourth submittal, extra plan review fees. Stop and have someone read the letter against the sheets.12

WHAT THE CITY WILL ASK FOR

Expect to be asked for these.

  • An answer to every comment

    Cities send the comments as marks on your sheets or as a list in the portal. Chandler’s portal shows them, and Phoenix lets you enter a response when you resubmit. Answer each one, even when the answer is "no change, because…".11,5

  • Corrected sheets in the city’s format

    Same file names (Phoenix, Chandler), same page order with new sheets at the end (Chandler), a complete revised set with delta and cloud on every change (Glendale). Mesa, Gilbert and Tempe pages we read give no format rule, so ask the permit counter.5,12,21

  • The documents the comment points to

    A comment often says "provide" something: a panel schedule (Chandler, for a new sub-panel), a plot plan with property lines, structural details, or sealed truss calculations. Send those as separate files where the city asks. Glendale asks for other documents as separate PDFs from the plan set.11,21

  • Engineer seal where required

    Chandler wants sealed truss calculations or a waiver sealed by an Arizona-registered engineer. Mesa wants engineer-sealed drawings on new homes and pools. Glendale has the engineer of record seal the special inspection form.11,6,23

  • A written extension request before the date

    Chandler takes a written request on its extension form, with a reason, to extend an approval or permit up to 180 days. Scottsdale’s building official may grant extensions of up to 180 days each, requested in writing with cause shown. Gilbert links its own extension form.14,9,16

  • A call to the permit office when a comment is unclear

    The city pages we read describe no formal meeting with the plans examiner for a home. They list contacts: Chandler Development Services at 480-782-3074, Glendale at 623-930-2800 or permits@glendaleaz.com, Tempe at 480-350-4311 or permitcenter@tempe.gov, Phoenix Planning and Development at 602-262-7811. Scottsdale links a separate "Request for Preliminary Plan Review Meeting" page and says houses typically need no pre-application meeting. Ask what a comment means before you change anything.13,21,19,4,9

YOUR CITY’S RULES

Your city’s rules.

Short notes from each city’s own pages. Rules change, so open the linked page for the current text.

  • Phoenix2,3,5,4

    • For remodels and some additions, staff contact you to pick up the plans; you correct them and resubmit.
    • In the electronic system, corrected files must have the exact same file names as the originals so versions can be compared.
    • Phoenix’s standard-plan guideline says a revision to approved plans is sent as revised sheets only, with a cloud and delta, and a change that adds scope needs a new application and fee. The page that states this is for standard plans, so ask if your job is custom.
    • The pages we read do not say how long an application stays active, who may apply, or how many corrections rounds are included. Ask Planning and Development.
  • Mesa6,7,8

    • You get a system email when new information is needed, then upload revised plans in the DIMES portal. The page mentions a second and third round but states no maximum and no extra fee, so ask.
    • Building items and zoning items sit on separate checklists, so check both against the letter.
    • Mesa says a permit stays valid for 180 days after it is issued. The page does not say how long plans stay approved before a permit is bought.
    • Owner-occupied projects may not need a licensed contractor, and the page points to the Registrar of Contractors. New homes and pools need engineer-sealed drawings.
  • Scottsdale9

    • A set that needs changes is sent back to the applicant or their design professional; you submit amended plans and the process starts over.
    • An application is deemed abandoned 180 days after the last completed correction or approval step, unless you pursue it in good faith or a permit is issued.
    • The building official may grant one or more extensions of up to 180 days each, requested in writing before the date with justifiable cause.
    • If no permit is bought 180 days after plan approval, plans and fees must be submitted again. You apply in the SPUR portal.
  • Chandler13,12,14,11

    • Comments are viewable, and corrected plans uploaded, in the city’s online portal. Keep the original file names and page order, and put any new sheets at the end.
    • Chandler says incomplete packages can add rounds and extra plan review fees if a fourth submittal becomes necessary. The page does not give the amount, so ask.
    • Changes to approved plans go by email to plans.coordination@chandleraz.gov with the original permit number, a short description and a PDF of only the affected sheets.
    • Plan approvals and permits may be extended up to 180 days on a written request before expiration; an expired permit may be reinstated within one year for half the original permit fee.
    • A licensed contractor must get the permit unless the owner does the work, and always for a home you rent out.
  • Gilbert15,16

    • Building submittals go through the One Stop Shop portal. The estimated plan review fee is paid at the first application.
    • The permits page links a permit extension form and the Development Services fee schedule. The pages we read do not state how many rounds are included or an extra-round fee, so check the fee schedule and ask.
  • Tempe17,18,19,20

    • All submittals are 100% electronic through the Tempe Citizen Access Portal, and a registered account is required. Plans follow the city’s E-Plan Review Submittal Guidelines.
    • The plan review page lists a "Registered Design Professional Required" handout. Read it before you decide to answer an engineering comment yourself.
    • Questions go to permitcenter@tempe.gov or 480-350-4311. The pages we read do not state how long an application stays active or the extra-round fee; the fees page is linked in the sources.
  • Glendale21,22,23,24

    • Corrections arrive by email with a marked-up package. You upload a new complete set of revised drawings and mark every change with a delta and a cloud.
    • Plans go in as one complete PDF set and other documents as separate PDFs. Files that do not follow the city’s standards may be rejected.
    • The homeowner or a licensed contractor may apply, and for a home improvement the homeowner may prepare the drawings if they are accurate, legible and complete.
    • A permit lapses if work is not started or an inspection not passed in the city’s period (the pages say about six months or 180 days, so ask). Extending costs 50 percent of the original permit fee and renewing an expired permit 100 percent, as the city’s Q&A states.

COSTS TO EXPECT

Our fee, and building costs where a public source gives one.

  • Reinstating an expired permit in Chandler, per its extension form (a city fee, not ours)14

    Building cost, not our fee

    one-half of the original permit fee

  • Glendale’s extension of a permit, as its Q&A states (a city fee, not ours)23

    Building cost, not our fee

    50 percent of the original permit fee

  • Glendale’s renewal of an expired permit, as its Q&A states (a city fee, not ours)23

    Building cost, not our fee

    100 percent of the permit fee

FAQ

Frequently asked questions

  • Does a corrections letter mean my plans were denied?

    No. The pages we read describe it as a normal step: the city returns the plans, you correct them and resubmit. It means the city wants specific things fixed or shown. Answer it carefully and completely.

  • Do I need a written response letter?

    The residential pages we read do not require a response letter. Phoenix’s electronic system lets you enter a response when you resubmit, and Chandler’s portal shows the comments. Even where it is not required, a one-page list answering each comment, sheet by sheet, makes the reviewer’s job easier. Ask your city what it prefers.

  • How many correction rounds are included before extra fees?

    It depends on the city, and most pages we read do not say. Chandler says incomplete packages can add rounds and extra plan review fees if a fourth submittal becomes necessary, without giving the amount. Mesa mentions a second and third round and no maximum. Gilbert and Tempe link fee schedules in the sources. Ask your city before you assume a number.

  • How long does my application stay open?

    Scottsdale calls it abandoned 180 days after the last completed correction or approval step and allows written extensions of up to 180 days each. Chandler extends plan approvals and permits up to 180 days on a written request before expiration. Phoenix, Mesa, Gilbert and Tempe pages we read do not give a plan limit, so ask. Do not wait until the last week.

  • Can I answer the corrections myself as the owner?

    Often yes for drawing fixes. Glendale lets a homeowner prepare drawings for a home improvement if they are accurate, legible and complete, and Chandler lets the owner who does the work get the permit. State law covers owners building for their own use, not for sale or rent. Comments that need a seal, calculations or a redesign are not yours to answer alone.

  • When does a correction need an engineer’s seal?

    When it asks for structural calculations or a sealed design. The pages we read name sealed truss calculations or a waiver (Chandler), engineer-sealed drawings for new homes and pools (Mesa), and a special inspection form sealed by the engineer of record (Glendale). A licensed engineer does and seals that work. We draw the plans; we are not an engineering firm.

  • Can I ask the plans examiner to explain a comment?

    The city pages we read do not describe a formal meeting for a home, but they list phone numbers and emails for the permit office. Scottsdale links a separate page to request a preliminary plan review meeting. Call, write down who you spoke to, and ask for the answer by email so you have it on file.

  • What does Archipartners Design do with a corrections letter?

    If we drew the plans, we answer the city’s comments on our own scope, and if the city flags an error in our drawings we fix it. A design change you ask for, or outside engineering, is quoted first, with the price agreed in writing before we start. If we did not draw the plans, send us the letter and the plans. We read the letter, tell you which comments we can handle and which need an engineer or a redesign, and quote it. We are not an architect, and we do not seal or stamp. We reply within one business day.

SOURCES

Where each fact comes from.

Every number in a superscript links to the official page below. Opens in a new tab.

  1. A.R.S. 32-1121 — Licensing exemptions (owner-builder)

    Arizona Legislature · checked November 2026

  2. Residential process overview

    City of Phoenix · checked November 2026

  3. Residential additions and remodels

    City of Phoenix · checked November 2026

  4. Standard plans, residential guidelines (PDF)

    City of Phoenix · checked November 2026

  5. Electronic plan review project tasks (PDF)

    City of Phoenix · checked November 2026

  6. Residential construction

    City of Mesa · checked November 2026

  7. Residential plan review

    City of Scottsdale · checked November 2026

  8. Homeowner building permit manual, April 2026 (PDF)

    City of Chandler · checked November 2026

  9. Electronic plan review

    City of Chandler · checked November 2026

  10. Plan review / permit extension request, form UDM-041 (PDF)

    City of Chandler · checked November 2026

  11. Plan review

    Town of Gilbert · checked November 2026

  12. Plan review

    City of Tempe · checked November 2026

  13. Residential plan review

    City of Tempe · checked November 2026

  14. Permit Center

    City of Tempe · checked November 2026

  15. Building safety fees

    City of Tempe · checked November 2026

  16. Submit electronic plans

    City of Glendale · checked November 2026

  17. Building permits

    City of Glendale · checked November 2026

  18. Building permits Q&A

    City of Glendale · checked November 2026

  19. Permit extension or renewal

    City of Glendale · checked November 2026

WHEN YOU’RE READY

Want us to draw it?

Send us the address and what you want built. We reply within one business day.

The City Sent Corrections: a Field Guide to answering a plan review letter · Archipartners Design