Unpermitted Work Field Guide: buying, selling or legalizing a room, garage or patio built without a permit

Ten checks, the stop signs, and what seven Phoenix-area cities say about work built without a permit, before you buy, sell or pay for plans.

A room, garage conversion, patio enclosure or casita built without a permit is common, and it often comes up when a home is being sold. This guide shows how to find out whether a permit exists, what seven cities say about fixing it, and when to stop and call a professional. It is not legal advice. For contract or disclosure questions, ask a real estate attorney or your agent. APD draws as-built plans of what is already there. An engineer licensed in Arizona seals any structural work. We reply within one business day.

Updated November 23, 2026 · Free · one email with the link

Built from the city pages of Phoenix, Mesa, Scottsdale, Chandler, Gilbert, Tempe, Glendale. Anywhere else, check your own city’s page.

One email with the link. We don’t sell your address; you can unsubscribe with one click.

5-MINUTE GO / NO-GO

Answer these before you spend money.

Each check is a yes or no. A “no” or a “don’t know” is something to settle first.

  1. Is there a permit record for this room, garage or patio?

    Look up the address on the city’s permit search before you buy, sell or pay for drawings. Phoenix’s search shows permit history, with older records at its Records Center. Mesa’s portal shows records since 2017, and older ones need a records request. Scottsdale’s Property Information request lists permits, plan reviews and cases. Chandler and Tempe have address lookups too. No record may mean no permit, or only an old record, so ask the city.18,23,27,7,33

  2. If there is a permit, did it pass final inspection and cover this exact work?

    Phoenix tells owners to read the permit’s scope against the work or the notice. The permit must cover that work and have final inspection approval, shown as done in its status. A listing that starts with a complaint or case code is an investigation, not a permit. A permit for a patio cover does not legalize a room built under it.18

  3. Is there a notice of violation or an open city case on the property?

    Phoenix may record a notice of violation with the Maricopa County Recorder, and it runs with the land until a release is recorded. Ask the city for open cases on the address. Scottsdale has a case status lookup. A buyer inherits the property, so ask before you sign.16,18,27

  4. Do you know who built it, and when?

    Phoenix may waive or reduce its extra fees when the work was done by a previous owner. You still need a permit to make it legal. Ask the seller what they know, and write down what you learn. Other cities’ pages we read do not say how they treat work done by a previous owner, so ask.17,21

  5. Does it meet today’s zoning: setbacks, height and parking?

    Legalizing means meeting today’s rules, not the rules from when it was built. Scottsdale says old unpermitted ADUs are not grandfathered. Phoenix says unpermitted buildings must be legalized before an ADU permit. Gilbert says a garage cannot be converted unless the same number of covered parking spaces remain. Ask zoning staff about your lot before you spend money.12,3,9

  6. Were the electrical, plumbing and gas done by a licensed contractor, with permits?

    Chandler says work that needs a permit needs a licensed contractor unless the owner does the work, and points to A.R.S. 32-1121(A). Scottsdale lists separate electrical, plumbing and gas, and mechanical permits. Check a contractor’s license on the Arizona Registrar of Contractors search. Hidden wiring and gas lines are the work an inspector cares about most.7,26,14

  7. If the city asks, can walls, ceiling or floor be opened for an inspector?

    None of the city pages we read explains how its inspectors treat work already covered by drywall or flooring. Phoenix says an investigation happens before a permit can be issued for unpermitted work. Mesa’s page sends questions about unpermitted work to Permit Services. Ask your city early, and plan for the cost of patching and painting afterward.21,24

  8. If it has a bedroom, does the bedroom have a code escape window or door?

    The residential code requires an emergency escape opening in a sleeping room. In the 2024 IRC this is section R319, and Phoenix amends it. Phoenix, Mesa, Chandler and Glendale enforce the 2024 edition. Scottsdale enforces the 2021 edition and Gilbert the 2018 edition, so the section number differs there. Tempe allows the 2018 or 2024 codes through 2026. Ask your city which edition applies.2,4,6,11,5,10,8

  9. Is the home in an HOA, and did the HOA approve the work?

    Chandler says it does not enforce HOA rules and that the owner must know and follow them. A city permit does not replace the association’s approval. Ask the HOA for its approval record in writing.7

  10. Does the work sit inside the property lines and off any easement?

    Chandler says the owner is responsible for locating the property lines, and its plot plan must show them with distances. Arizona’s ADU law, for one case, bars building an ADU on a public utility easement without each utility’s written consent. A survey settles this. A permit cannot fix work on a neighbor’s land.7,1

STOP SIGNALS

If you see any of these, pause.

  • The work crosses a property line or sits on an easement

    Stop and get a survey. A city permit does not give you the right to build on a neighbor’s land or a utility’s easement. Arizona’s ADU law, for example, requires written consent from each utility to build an ADU on a public utility easement. Talk to a real estate attorney before you buy or sell.1,7

  • A bedroom with no escape window or door

    Do not let anyone sleep there until the opening is fixed. An escape opening is a life-safety rule in the residential code, and Phoenix amends it for new sleeping rooms. Window size and sill height are what a plan reviewer looks at first.2

  • A gas appliance or gas line installed without a permit

    Stop using it until a licensed contractor has it permitted and inspected. Scottsdale lists plumbing permits for gas work, and Phoenix’s owner guide lists gas line projects among the work that needs a permit. A bad gas connection is a fire and carbon monoxide risk, and a buyer’s inspector will ask about it.26,22

  • Structural changes with no engineer

    A removed or moved wall, a cut beam, a new opening or a second story needs an engineer licensed in Arizona to look at it. Scottsdale, for an as-built wall, asks for an assessment sealed by an Arizona engineer or architect before it will issue a permit. Phoenix lists wall removal or relocation as work that needs a permit. APD draws the plans. An engineer does the structural check and seal.28,22

  • The city has already opened a code-enforcement case

    Read the notice first and note any date it sets. Phoenix tells owners with a notice of violation to apply for a permit by the date on the notice, and may issue civil citations if work continues after a stop work order. Mesa and Chandler describe a notice, then a re-inspection, then a citation. Call the city before you hire anyone, and talk to an attorney if a sale is pending.15,16,25,30

  • Someone is living or renting in space that is not legal

    Phoenix’s code makes it a violation to occupy or maintain a building that was built or altered without a required permit. Chandler warns that a lender may refuse a loan when county records do not match the house, and that insurance may not cover problems from unpermitted work. Do not rent the space until it is permitted, and ask your insurer and lender what they require.21,7

WHAT THE CITY WILL ASK FOR

Expect to be asked for these.

  • The permit history and any open cases for the address

    Start with the city’s own lookup (see the city notes below). Ask for permits, inspections and any open case or recorded notice. In Phoenix, a recorded notice of violation is closed by a release recorded with Maricopa County once the permit has passed final inspection.18,23,27,33

  • A permit application for the work that already exists

    Phoenix says an investigation is made before a permit may be issued for unpermitted work, and its notice page says to apply no later than 30 calendar days after the date on a notice of violation. Glendale’s code also calls for a special investigation before a permit for work started without one. Other cities’ pages we read do not describe a separate path, so ask each city how it wants this handled.15,21,35

  • Drawings of what is built today

    Chandler’s plot plan must show the property lines, every building on the lot and the distances from new structures to the lines. For the rest (floor plan, structural, electrical), the pages we read do not list a checklist for existing work, so ask your city what it wants. This is the part APD draws: a measured as-built set, with an engineer for structural.7

  • Extra fees on top of the permit fee

    Phoenix charges an investigation fee, twice the permit fee and a job-site meeting fee. Scottsdale and Tempe publish a double fee. Chandler says it may charge a double fee. Glendale’s code adds an investigation fee set by council resolution. Mesa’s and Gilbert’s pages we read do not state one, so ask. Phoenix may waive or reduce the extras when a previous owner did the work.19,17,26,32,7,35

  • A sealed assessment from an engineer or architect, where the structure is in doubt

    Scottsdale describes this only for walls: an Arizona engineer or architect submits a sealed assessment of the as-built wall, city staff check it, then a permit and an inspection follow, and the wall stays in violation until all steps are done. For rooms and other structures, ask your city whether it wants the same.28

  • A job-site meeting and inspections to close the permit

    Phoenix’s code amendments schedule a job-site meeting after the permit is issued, so the inspector and the owner can agree on the corrections and the inspection schedule. A recorded notice is released only after the permit passes final inspection. Ask your city what its inspector will need to see.21,18

YOUR CITY’S RULES

Your city’s rules.

Short notes from each city’s own pages. Rules change, so open the linked page for the current text.

  • Phoenix18,20,19,17,15,16

    • The building permit search shows permit history. For older records, the Records Center at City Hall helps.
    • Fee schedule approved 12/17/2025: an investigation fee of $250 or the permit fee, whichever is greater; the permit fee for work started without a permit is twice the normal fee; a job-site meeting is $195 an hour per inspection discipline, with a $390 minimum.
    • Phoenix may waive or reduce the investigation and extra permit fees when you can show a previous owner did the work. An owner who agrees to remove the work pays the investigation fee but may have the double fee waived or reduced.
    • A notice of violation can be recorded with Maricopa County and runs with the land. The city’s non-permitted construction page says to apply for a permit no later than 30 calendar days after the date on the notice.
  • Mesa23,24,25

    • The DIMES portal shows records since 2017 and needs no account to search. Use the address in quotation marks. Older records and zoning letters need a document retrieval request, and fees apply.
    • Mesa’s residential page says converting non-livable space into livable space needs a construction permit. It does not say what happens to work already done without one, so ask Permit Services.
    • Code Compliance leaves an inspection notice, then mails a Notice of Violation, and a citation can follow if the problem continues. Only a supervisor can extend a case beyond 28 days.
  • Scottsdale26,27,28

    • The city says work completed without a permit is fined an amount equal to double the permit fee.
    • The Property Information request lists permits issued, plan reviews, cases and property records for an address. There is also a case status lookup. Scottsdale is moving projects to its SPUR portal, so ask the Records office which tool covers your address.
    • The Records page says building plans are destroyed after a set period following completion, so original plans for an older job may not exist. As-built drawings can fill that gap.
    • For a wall built without a permit, an Arizona engineer or architect submits a sealed assessment, the city reviews it, and the wall stays in violation until the permit is finaled.
  • Chandler7,30

    • The Homeowner Building Permit Manual (April 2026) says any project under construction or completed without a permit may be charged a double permit fee.
    • Working without a permit can bring a Legal Notice or an Order to Comply, and the city can order non-compliant work, such as a room addition, removed at the homeowner’s cost.
    • The manual warns that problems arise at sale when County Assessor records do not match the house, that FHA will not provide a loan in that case, and that homeowner’s insurance may not cover problems from non-permitted work.
    • The manual points to the city’s permit portal: open the Development Services tab and enter the address. Extra detail needs a records request.
  • Gilbert9,31

    • Town code needs a building permit for any building of 200 square feet or more, and for a smaller shed if it has electrical or plumbing or is connected to the house.
    • Gilbert’s code compliance FAQ says a garage cannot be converted to another use unless the same number of covered parking spaces remain.
    • We did not find a public address search or a stated penalty for unpermitted work. The One Stop Shop portal handles permits and inspections, so ask Development Services how to see permit history and what fees apply.
  • Tempe32,33,34

    • The city’s fee schedule lists “Work without Permits” as double the permit fees.
    • The Citizen Access portal has a “Look Up Property Information” tool that searches by address, parcel, owner, record number or licensed professional.
    • The Building Safety Division investigates building code violations such as construction without permits, and its inspections page has a report form.
  • Glendale35,36

    • The 2024 building code amendments say that when work has started without a permit, a special investigation is made before a permit may be issued.
    • An investigation fee is charged in addition to the permit fee, whether or not a permit is issued. The amount is set by council resolution, so ask the city for the current figure.
    • Code Compliance sends a notice with a correction deadline, then inspects again. We did not find a public address search for permit history, so ask Development Services.

COSTS TO EXPECT

Our fee, and building costs where a public source gives one.

  • Phoenix’s fees for work done without a permit, per its fee schedule approved 12/17/2025. These come on top of the normal permit fee. Not our fee19

    Building cost, not our fee

    Investigation fee $250 or the permit fee, whichever is greater. Permit fee 2 times the normal fee. Job-site meeting $195 per hour per inspection discipline, $390 minimum.

  • Scottsdale’s fine for work completed without a permit, as the city states it. Not our fee26

    Building cost, not our fee

    An amount equal to double the permit fee

  • Tempe’s listing for work without permits in its schedule of fees. Not our fee32

    Building cost, not our fee

    Double the permit fees

  • Chandler’s homeowner manual on a project under construction or finished without a permit. Not our fee7

    Building cost, not our fee

    May be charged a double permit fee

FAQ

Frequently asked questions

  • Can I get a permit now for something already built?

    Phoenix, Glendale and Tempe describe an investigation or a fee schedule for work done without a permit, and Phoenix’s notice page tells owners to apply for a permit. Whether your work can be made legal depends on today’s zoning, the building code and what an inspector finds. We cannot say in advance. Ask your city, then have as-built plans drawn.

  • Will I pay double?

    Phoenix, Scottsdale and Tempe publish a double fee, and Chandler says it may charge one. Phoenix adds an investigation fee and a job-site meeting fee, and may waive or reduce the extras when a previous owner did the work. Glendale adds an investigation fee. Mesa’s and Gilbert’s pages we read do not state one. Ask your city for the current figures.

  • I bought a house with an unpermitted room. Is it my problem now?

    The permit and the safety fixes fall on the current owner, because a recorded notice runs with the land in Phoenix. Phoenix’s waiver procedure lets it waive or reduce its extra fees when the work predates your ownership. Whether you can claim anything from the seller is a legal question. Ask a real estate attorney.

  • Will the city make me tear it down?

    Chandler says it can order non-compliant work, such as a room addition, removed at the owner’s cost. Phoenix has a demolition-permit route for work an owner agrees to remove. Which way your case goes depends on what is built and what the city finds. We cannot say in advance.

  • Do the walls have to be opened for inspection?

    The city pages we read do not say. Phoenix says an investigation comes before a permit for unpermitted work, and Mesa sends questions about unpermitted work to Permit Services. Ask your city before you pay for plans, so you know what an inspector may want to see.

  • What is an as-built plan set?

    It is a measured drawing of what exists today: a site plan with the property lines, floor plans and the other sheets your city asks for. It shows what is there, not what you wish were there. An engineer licensed in Arizona handles any structural check and seal. APD draws the plans. Send us the address and photos, and we reply within one business day.

  • Does the seller have to tell the buyer about unpermitted work?

    That is a legal question, so ask a real estate attorney or your agent. The state land-division disclosure law we found, A.R.S. 33-422, covers certain land sales in unincorporated areas of a county, not an ordinary home sale inside a city. We do not give legal advice.

  • Does my HOA matter if the city signs off?

    Yes. Chandler says it does not enforce HOA rules and that you must know and follow them. A city permit does not replace the association’s approval. Get the HOA’s answer in writing.

SOURCES

Where each fact comes from.

Every number in a superscript links to the official page below. Opens in a new tab.

  1. A.R.S. 9-461.18 — Accessory dwelling units

    Arizona Legislature · checked November 2026

  2. 2024 IRC amendments (PDF)

    City of Phoenix · checked November 2026

  3. Beginner’s guide to ADUs (PDF)

    City of Phoenix · checked November 2026

  4. Mesa building code

    City of Mesa · checked November 2026

  5. Building codes

    City of Scottsdale · checked November 2026

  6. Amendments to the 2024 International Codes (PDF)

    City of Chandler · checked November 2026

  7. Homeowner building permit manual (PDF)

    City of Chandler · checked November 2026

  8. Building code adoption dates

    Town of Gilbert · checked November 2026

  9. FAQ — Municipal Code and Land Development Code

    Town of Gilbert · checked November 2026

  10. Building codes and amendments

    City of Tempe · checked November 2026

  11. Building codes

    City of Glendale · checked November 2026

  12. ADU FAQs, October 2025 (PDF)

    City of Scottsdale · checked November 2026

  13. A.R.S. 33-422 — Land divisions; recording; disclosure affidavit

    Arizona Legislature · checked November 2026

  14. Contractor search

    Arizona Registrar of Contractors · checked November 2026

  15. Non-Permitted Construction

    City of Phoenix · checked November 2026

  16. 2024 IBC Chapter 1 amendments, Section 114 (PDF)

    City of Phoenix · checked November 2026

  17. Residential construction

    City of Mesa · checked November 2026

  18. Report a code violation

    City of Mesa · checked November 2026

  19. Home improvement

    City of Scottsdale · checked November 2026

  20. Records

    City of Scottsdale · checked November 2026

  21. Walls and fences

    City of Scottsdale · checked November 2026

  22. Code enforcement

    City of Scottsdale · checked November 2026

  23. Code enforcement

    City of Chandler · checked November 2026

  24. One Stop Shop customer service

    Town of Gilbert · checked November 2026

  25. Appendix A, Schedule of fees and charges (Table 1-A and following)

    City of Tempe (Municode) · checked November 2026

  26. Look up property information (Citizen Access)

    City of Tempe · checked November 2026

  27. Code compliance: common inquiries

    City of Glendale · checked November 2026

WHEN YOU’RE READY

Want us to draw it?

Send us the address and what you want built. We reply within one business day.

Unpermitted Work Field Guide: buying, selling or legalizing a room, garage or patio built without a permit · Archipartners Design